Construction progress

«LIFE STORY» construction progress:

1q 20204q 2021

We share news from the LIFE STORY construction site as of March 1, 2021:

  • 42 piles were drilled.

We share news from the LIFE STORY construction site as of February 15, 2021:

  • 12 piles were drilled.
  • Installed an additional drilling rig.

We share news from the LIFE STORY construction site as of February 08, 2021:

  • We continue to drill piles, 20 are executed

We share news from the LIFE STORY construction site as of February 01, 2021:

  • Began to drill the first piles

Video

Photo

Video

Photo

Video

Photo

Video

Photo

Sales
office

Kyiv

72 V. Vasylkivska Street
Olimpiiskyi BC, the 26th floor

13-А, Metrolohichna str
near the construction site

 

+38 044 499 88 40

Lviv

11, Hrushevsky str.
 

30, Maloholoskivska str
 

Pasichna str, opposite №127

+38 096 394 00 44

Receive construction progress reports

Thank you!

You are subscribed to news
about «LIFE STORY»

Choose an apartment Phone callback